Crowne Plaza Hotel, Turkey
Building Information
- Location: Istanbul, Turkey
- Number of floors: 5F
- Total floor area: 22,500 m2
- Completion: 2008
Equipment Installed
VRV (Heat pump and Heat recovery)
with intelligent Touch Manager
Overview
This was a retro-fit project, starting from 2005. As the hotel building is a historical
structure, they have false ceiling and shaft problems.
The owner and designer favored the VRV system due to no mechanical
installation space. After we told the owner and designer how the VRV
system offers 20% energy efficiency improvement compared to existing system as well as easy operation and
maintenance, they decided to go with the VRV system. A heat recovery
system was used for the guest rooms and heat pump system was installed for public space. Outside air
processing units were used in public space to keep the air fresh.